A company prepares its budget every month by adding a new month and dropping the month just completed, so that a twelve-month budget is always available. What is this called?

Answer and explanation

Correct answer: B. A rolling budget

  1. Step 1: A rolling (continuous) budget is updated regularly by adding a future period as each period ends.
  2. Step 2: The other three differ in how the figures are built.
Answer
A rolling budget.
Why not the others: A zero-based budget: Zero-based budgeting starts from nothing and requires each activity to be justified. An incremental budget: Incremental budgeting takes last year's figures and adds a percentage. A flexible budget: A flexible budget changes with activity levels, not with the passage of time.