Using the same labour data (standard 2 hours per unit at £9, 2,000 units made, 4,200 hours paid of which 150 were idle), what is the labour efficiency variance?

Answer and explanation

Correct answer: D. £450 adverse

  1. Step 1: Standard hours for 2,000 units = 4,000 hours.
  2. Step 2: Hours worked = 4,200 paid − 150 idle = 4,050 hours.
  3. Step 3: Efficiency variance = (4,000 − 4,050) × £9 = £450 adverse.
Answer
£450 adverse.
Why not the others: £450 favourable: More hours were worked than the standard for the output, so it is adverse. £1,800 adverse: This compares hours paid (4,200) with standard hours (4,000) and ignores that idle hours are treated separately: 200 hours × £9. £1,350 adverse: This is the idle time variance, not the efficiency variance.

Practise more Standard costing and variance analysis.

Free questions with an explanation for every one, and full timed ACCA Applied Knowledge (BT, MA, FA) mock tests.