Total labour costs were £39,060 against a standard labour cost for the output of £36,000. The rate variance was £1,260 adverse, the efficiency variance £450 adverse and the idle time variance £1,350 adverse. What is the total labour variance and is the analysis consistent?

Answer and explanation

Correct answer: C. £3,060 adverse, and the three variances add up to it

  1. Step 1: Total labour variance = standard cost £36,000 − actual cost £39,060 = £3,060 adverse.
  2. Step 2: Rate £1,260 + efficiency £450 + idle time £1,350 = £3,060.
  3. Step 3: The analysis is complete and consistent.
Answer
£3,060 adverse, and the three variances add up to it.
Why not the others: The three variances total £3,060, not £2,700. Actual cost is higher than standard, so the total is adverse. All three variances increase total cost above the standard.

Practise more Performance measurement.

Free questions with an explanation for every one, and full timed ACCA Applied Knowledge (BT, MA, FA) mock tests.

Total labour costs… | ACCA Applied Knowledge (BT, MA, FA)