Worker A can complete a construction task in 12 days, while Worker B can complete the same task in 18 days. Working together, in how many days can they finish the task?

Answer and explanation

Correct answer: B. 7.2 days

  1. Step 1: Combined rate per day: 1/12 + 1/18 = (3 + 2) / 36 = 5/36 task per day. Step 2. Total days required: 36 / 5 = 7.2 days. Answer: 7.2 days. Why not the others: 6.0 days is half of 12; 8.0 days is an arbitrary guess; 7.5 days divides 15 by 2.