Four workers need 6 days for a job. How many days do eight workers need at the same rate?

Answer and explanation

Correct answer: C. 3 days

  1. Step 1: Twice as many workers need half the time. Step 2. 6 / 2 = 3 days. Answer: 3 days. Why not the others: 12 days doubles the time.