8 workers need 9 days for a job. How many days would 6 workers need at the same pace?

Answer and explanation

Correct answer: A. 12

  1. Step 1: Total work = 8 x 9 = 72 worker-days. Step 2. 72 / 6 = 12 days. Answer: 12. Why not the others: 6.75: direct proportion was used instead of inverse. 11: the numbers were added and subtracted. 3.375: an extra factor of 2 was applied.