5 workers need 12 days for a job. How many days would 10 workers need at the same pace?

Answer and explanation

Correct answer: B. 6

  1. Step 1: Total work = 5 x 12 = 60 worker-days. Step 2. 60 / 10 = 6 days. Answer: 6. Why not the others: 24: direct proportion was used instead of inverse. 7: the numbers were added and subtracted. 12: an extra factor of 2 was applied.