One worker finishes a job in 10 days and another worker finishes it in 15 days. How long will they take if they work together?

Answer and explanation

Correct answer: B. 6 days

  1. Step 1: Their daily rates are 1/10 and 1/15, which add up to 25/150, so the time is 150/25 = 6 days. Answer: 6 days. Why not the others: 12.5 days: averages the two times. 25 days: adds the two times. 5 days: subtracts the times.