Principle: Under Section 73 of the Contract Act, ordinary damages are those that arise naturally in the usual course of things from the breach.
Facts: A contracts to deliver machinery to B by 1 June. A delays delivery by 2 months. B loses normal production profits of ₹50,000 and an extraordinary government contract worth ₹5,00,000 (which was never disclosed to A). What damages can B recover?
Answer and explanation
Correct answer: A. Only ₹50,000 normal production profits, as extraordinary profits were not communicated
- Step 1: Apply the rule in Hadley v. Baxendale incorporated into Section 73 of the Indian Contract Act.
- Step 2: Damages are recoverable for losses that naturally arise in the usual course of things, or which were in contemplation of both parties at the time of contract.
- Step 3: Normal production profits of ₹50,000 are ordinary damages. The extraordinary profit of ₹5,00,000 was remote and uncommunicated, and cannot be recovered.
Answer
Only ₹50,000 normal production profits, as extraordinary profits were not communicated.
Practise more Contract Law: Specific Performance, Quasi-Contracts and Damages.
Free questions with an explanation for every one, and full timed CLAT UG mock tests.
More Contract Law: Specific Performance, Quasi-Contracts and Damages questions
- Principle: Quasi-contracts under Section 70 of the Indian Contract Act require that a person lawfully do something for another, not intendin…
- Principle: An agreement in restraint of trade is void under Section 27 of the Indian Contract Act, except when relating to the sale of goodw…
- Principle: Specific performance of a contract is granted when monetary compensation is inadequate relief, notably in contracts concerning im…
- Principle: A finder of lost goods has the same responsibility as a bailee under Section 71 of the Indian Contract Act.
Facts: X finds a diam… - Principle: Novation of contract occurs when parties substitute a new contract for an existing one, discharging the original contract.
Facts… - Principle: A contingent contract to do or not do anything on an uncertain future event becomes void if the event becomes impossible.
Facts…