Six workers build a wall in 10 days. Working at the same pace, how many days would 15 workers need?

Answer and explanation

Correct answer: B. 4 days

  1. Step 1: Total work = 6 x 10 = 60 worker-days. Step 2. With 15 workers: 60 / 15 = 4 days. Answer: 4 days. Why not the others: The quantities are inversely proportional; the wrong options treat them as directly proportional or subtract.