Four workers paint a wall in 6 days. Working at the same rate, how long do 8 workers need?

Answer and explanation

Correct answer: C. 3 days

  1. Step 1: Total work = 4 workers x 6 days = 24 worker-days. Step 2. With 8 workers the time is 24 / 8 = 3 days. Answer: 3 days. Why not the others: Time falls as workers rise (inverse proportion); it falls to a half, not to a third or by one day per worker.

Practise more Logical Reasoning.