A team of 12 civil servants can complete an administrative audit in 15 days. If 3 additional civil servants of equal efficiency join the team from the beginning, in how many days will the audit be completed?

Answer and explanation

Correct answer: B. 12 days

  1. Step 1: Total work in person-days = person-days. Step 2. New team size = civil servants. Step 3. Days required = days. Answer: 12 days. Why not the others: 10 assumes 18 people; 14 assumes 13 people. 11 does not fit.