A team of 12 civil servants can complete an administrative audit in 15 days. If 3 additional civil servants of equal efficiency join the team from the beginning, in how many days will the audit be completed?
Answer and explanation
Correct answer: B. 12 days
- Step 1: Total work in person-days = person-days. Step 2. New team size = civil servants. Step 3. Days required = days. Answer: 12 days. Why not the others: 10 assumes 18 people; 14 assumes 13 people. 11 does not fit.
Practise more Kemampuan Numerik dan Logika Aritmetika.
Free questions with an explanation for every one, and full timed CPNS Indonesia mock tests.
More Kemampuan Numerik dan Logika Aritmetika questions
- Find the next number in the series: 3, 7, 15, 31, 63, ?
- If a train traveling at a constant speed of 72 km/h crosses a 200-meter bridge in 20 seconds, what is the length of the train in meters?
- Find the missing term in the alternating series: 4, 18, 8, 14, 12, 10, ?
- A civil service department has 240 staff members. If 60% are analysts and the rest are administrators, and 75% of the analysts hold postgrad…
- If and , which statement correctly describes the relationship between and ?
- A vendor marks up office chairs by 25% above purchase price and then offers a 10% cash discount. What is the net profit percentage earned by…