Answer and explanation

Correct answer: A. A step-by-step description of how to do a task safely

  1. Step 1: The method statement sits with the risk assessment and sets out the safe sequence of work. Step 2. Workers should be briefed on it before starting. Answer: A step-by-step description of how to do a task safely. Why not the others: Costs, test results and inspection notices are different documents.