A householder hires one builder to renovate a kitchen. Under CDM 2015, who must prepare the construction phase plan?
Answer and explanation
Correct answer: C. The contractor
- Step 1: On a project with only one contractor, that contractor must draw up the construction phase plan. Step 2. A principal contractor is only appointed where there is more than one contractor. Answer: The contractor. Why not the others: HSE does not appoint contractors, and domestic clients' duties normally pass to the contractor.
Practise more Hazards, risk and site management.
Free questions with an explanation for every one, and full timed CSCS Card Health, Safety and Environment Test mock tests.
More Hazards, risk and site management questions
- What is the difference between a hazard and a risk on a construction site?
- You are about to start a task and notice the method statement does not match the conditions in front of you. What should you do?
- Which statement about a near miss is correct?
- Under the five steps to risk assessment, what is the first step?
- What is the main purpose of a site induction?
- What is a toolbox talk?