Under CDM 2015, who prepares and updates the health and safety file?

Answer and explanation

Correct answer: B. The principal designer for the whole project

  1. Step 1: The principal designer prepares the file for the client during design and hands it over at completion. Step 2. The principal contractor for the site prepares the construction phase plan. Answer: The principal designer for the whole project. Why not the others: The contractor prepares the plan, and neither the council nor every worker prepares the file.