A manager has the following tasks: a report due tomorrow for the board (urgent and important), reading trade magazines (not urgent, not important), planning next quarter's training (important, not urgent), answering a routine email from a supplier (urgent, not important). Which task should the manager schedule for later but not neglect, according to the urgent/important matrix?

Answer and explanation

Correct answer: A. Planning next quarter's training

  1. Step 1: The Eisenhower matrix has four quadrants.
  2. Step 2: Important but not urgent tasks are planned and scheduled.
  3. Step 3: Urgent and important are done at once; urgent but not important are delegated; neither are dropped.
Answer
Planning next quarter's training.
Why not the others: The report due tomorrow: This is urgent and important and must be done now. Reading trade magazines: This is neither urgent nor important and can be dropped or left. Answering the routine supplier email: This is urgent but not important and could be delegated.

Practise more Personal effectiveness, communication and ethics.

Free questions with an explanation for every one, and full timed ACCA Applied Knowledge (BT, MA, FA) mock tests.