Principle: Liquidated damages represent a genuine pre-estimate of loss agreed by parties, while a penalty is an extravagant sum intended to compel performance.
Facts: A contract provides that for each day of construction delay, the contractor pays ₹1,000, which reflects actual daily rental loss. Is this enforceable?

Answer and explanation

Correct answer: A. Yes, the court will award reasonable compensation not exceeding the agreed liquidated sum

  1. Step 1: Consult Section 74 of the Indian Contract Act 1872.
  2. Step 2: In Indian law, the distinction between liquidated damages and penalty is minimized: the court awards reasonable compensation not exceeding the penalty or sum stipulated.
  3. Step 3: Since ₹1,000 reflects genuine actual daily rental loss, it is reasonable compensation and enforceable.
Answer
Yes, the court will award reasonable compensation not exceeding the agreed liquidated sum.

Practise more Contract Law: Specific Performance, Quasi-Contracts and Damages.

Free questions with an explanation for every one, and full timed CLAT UG mock tests.

Principle: Liquidated damages represent a genuine… | CLAT UG